Funded program

WSM-E Water and Sanitary Sewer Replacement 2025 Ridglea Phase 4 Project

City of Fort Worth, Texas · Rehab and construction

Funded forAround Aug 2027From typical service life
Value$2M funded
Current contractorNot named
Get projects like this

Why reach out now

The council has funded the work.

From the council record“The City reasonably expects debt, as one or more series of obligations, may be issued or incurred by the City with an aggregate maximum principal amount not to exceed $2,000,000.00 for the purpose of paying the aggregate costs of the Project.”

Council record

What the city has done so far

  1. PlannedAug 11, 2026

    City expects debt up to $2,000,000 may be issued to pay aggregate costs of the Project.

    “The City reasonably expects debt, as one or more series of obligations, may be issued or incurred by the City with an aggregate maximum principal amount not to exceed $2,000,000.00 for the purpose of paying the aggregate costs of the Project.”